Laos inaugurates 1,070-MW Nam Theun 2 hydro project
The $1.45 billion project is co-owned by Electricite de France, the Lao government, the Electricity Generating Public Co. of Thailand and Italian-Thai Development.
After five years of construction and development costs of more than 1.4 billion dollars, the plant began supplying neighboring Thailand with power in March. Initially, the plant was expected to begin commercial operations by the end of 2009. Engineering problems delayed the project’s opening.
The project on the
Source: