ALSTOM (Thailand) is ready to bid on a coal-fired power plant project in Krabi. President Didier Farez said yesterday that the company had its own advanced environmental management technologies.
It will also provide the air-quality control systems composed of a wet flue gas desulphurisation system enabling reduction of sulphur oxides by more than 98 per cent, and electrostatic precipitators designed to capture particulate and dust emissions, with an efficiency of more than 99.9 per cent.
Upon its completion in 2018, the unit will produce 600 megawatts with the highest environmental performance and with atmospheric emissions reduced to meet the most stringent regulations, the company says.
Alstom has been present in Thailand for more than 40 years, having supplied more than 7 gigawatts of installed capacity in the country. It is constructing the 850MW North Bangkok combined cycle power plant, Block 2.
Ratanachai Namwong, Egat’s deputy governor for power-plant development, said the 800MW Krabi plant was expected to be tendered next month. The terms of reference will require the bidders to have the state-of-the-art technology called an ultra-supercritical pressure steam generator.
The winner could be announced this year.
The state enterprise will soon ask for the Cabinet’s consideration of the project’s environmental and health impact assessments.
When the plant starts supplying electricity in late 2019, it will be playing a key role in ensuring power security in the South, where demand has continued growing, Ratanachai said.
Source: http://www.nationmultimedia.com/business/Alstom-vows-to-bring-state-of-art-technology-to-Kr-30255819.html